Horizons features top industry experts shedding light on the most complex and exciting topics in water today. Hear about significant projects and innovations that have helped our clients achieve their water, wastewater, reuse, and water resources goals—and could help you achieve yours. Get insights into all things water®, all in one place.

We use MailChimp as our marketing platform. By clicking below to subscribe, you acknowledge that your information will be transferred to MailChimp for processing.
Learn more about MailChimp's privacy practices

Westerly Long-Term Residuals Plan

Hazen and Sawyer was selected by the Northeast Ohio Regional Sewer District (NEORSD) to develop a 20-year, long-term residual plan for the 35-mgd Westerly Wastewater Treatment Center. The results of this evaluation justified continued utilization of the existing multiple hearth incinerators while meeting the stringent regulatory schedule and deadlines.

Our Work

The recommended alternative in the long-term residuals plan was to maintain operation of the Westerly multiple hearth incinerators without importing solids from other municipalities (the lowest total net present value over the 20-year period). NEORSD implemented the recommended alternative for rehabilitation of the Westerly incinerators via a capital improvement project in 2016 and 2017.

email

Project Outcomes and Benefits

  • Identified 14 alternatives for solids handling processes and disposal methods
  • Evaluated maintaining current operations, exporting cake solids, exporting liquid solids, regional solids management methods and third-party public/provide partnership opportunities
  • Evaluated 20-year life-cycle costs including O&M for electricity, natural gas, polymer, hauling, labor and liquid stream treatment impacts
  • Evaluated qualitative (non-cost) factors including regulatory impacts, environmental impacts, implementation, maintenance of operation requirements, and social impacts
  • Engaged plant staff in the decision-making process
  • Met all critical milestones and delivered within compressed schedule to meet regulatory requirements
  • Project completed 15% under budget