The Harford County Department of Public Works is a facing challenges associated with a rapidly growing population and limitations in water supply and treatment capacity. By increasing the capacity of the Abingdon Water Treatment Plant from 10 to 20 mgd, the immediate demands for finished drinking water could be met while allowing time for the County to take a broader look at the supply and treatment issues over the longer term. Hazen and Sawyer evaluated technologies, performed facility planning, and developed cost-effective and innovative design documents to help the County meet their immediate needs for finished drinking water.
Hazen and Sawyer provided facility planning, preliminary engineering, final design, bid and construction-phase services for an expansion from 10 mgd to 20 mgd (with planning for buildout to 40 mgd) at the Abingdon Water Treatment Plant (WTP) in Harford County, MD. The Abingdon WTP, which treats water from either the Loch Raven Reservoir or the Susquehanna River, was originally constructed in the early 1990s using the Tricon bouyant-media upflow solids contact clarification process. Based on increasing demands in the County’s distribution system as well as the Base Realignment and Closure (BRAC) program, the capacity of the existing plant must be increased by year 2010.
The two raw water supplies are very different with respect to water quality, with the Susquehanna River being higher in turbidity and natural organic matter concentration. This difference is especially glaring when the Deer Creek Pump Station is first started-up. The Deer Creek PS is used to pump raw water from the Susquehanna River into the raw water pipeline serving the Abingdon WTP and City of Baltimore. Because this station sits unused for long periods of time, the water becomes stagnant and has historically been difficult to treat. Hazen and Sawyer performed bench-scale treatability testing to identify the chemical treatment regime and process design criteria required to ensure that the expanded plant can deliver drinking water in compliance with the Safe Drinking Water Act regulations regardless of the source.
The design of the project was completed in 2008, and bids from prequalified contractors were opened, with the low bid being within 1% of the engineer’s estimate. Design features of the project included:
In addition to the above, the design includes a unique backwash recycle process utilizing an innovative design that allows for filters to be physically disconnected from the main process and used for filtering plant backwash water during high recycle rate periods.
The complexities associated with yard piping at an existing facility necessitated the use of three dimensional (3-D) CAD in preparing the plans and profiles for the various pipelines required to connect the various treatment facilities together. The previous plant design stubbed-out several pipelines for future connections and the “repurposing” of these future connections for use on the new design project provided for significant cost savings due to easier pipeline construction.
Harford County was working on a new system model and facility plan for their First Zone, which included removal of the Abingdon Elevated Water Storage Tank (EWST) from the distribution system for use solely as backwash water storage on the plant site. Since the Abingdon EWST had previously served a useful function in offsetting surge due to finished water pumping station shutdowns and/or power loss scenarios, Hazen and Sawyer needed to perform surge modeling of the First Zone and associated pumping units to identify what problems might be caused by the removal of the tank. The results of the surge modeling indicated that a hydropneumatic surge tank (bladder-style) on the plant site would be required to avoid both detrimental high and low pressure surges in the distribution system.
on this project, or to discuss a similar project in your area, contact
Robert DiFiore, P.E. at .(JavaScript must be enabled to view this email address)© Copyright 2012 Hazen and Sawyer.