Innovative DAF Plant Meets City Sustainability Goals

Authors:

  • Peter H. Rice - City of Portsmouth, NH
  • Michael Greeley and Matthew Valade - Hazen and Sawyer

The new plant was placed online with no service interruptions to the consumers and has experienced increased filter run times and organics removal.

The original 3.5-mgd plant, a conventional settling/filtration facility, was built in 1958 as the primary source of drinking water for Portsmouth, New Hampshire.

The plant draws raw water from the Bellamy Reservoir, which exhibits low pH, low alkalinity, very low turbidity (less than 3 ntu) and high total organic carbon (avg ~ 8.0 mg/l; max ~ 17 mg/l).

The project was constructed on the existing site, carefully maximizing open, permeable space and minimizing the disturbance of vegetated land.

The design also maximized the use of existing facilities, such as this clearwell that was reused.

The City’s initiative to preserve natural vegetation demanded construction activities in close proximity to existing facilities which needed to be kept online throughout construction.

Designed to achieve LEED certification, the plant consumes 30 – 40% less energy than a typical comparable plant and is positioned to take advantage of natural elements such as the sun’s path and predominant winds.

Natural daylighting is used to provide both year-round light and solar heat gain in the winter, reducing energy costs.

Construction commenced in May 2009 and the plant was placed online during the summer of 2011.

The City of Portsmouth’s former Madbury water treatment plant was a 3.5 mgd conventional sedimentation and filtration plant constructed in the 1950s. At over 50 years old, the plant was starting to experience difficulty providing consistent and reliable treatment in accordance with current and potential future regulations. The City of Portsmouth piloted several treatment options, and decided to proceed with the design and construction of a new 4.0 mgd dissolved air flotation (DAF) and dual media filtration plant.

The project was constructed on the existing site, which is located in the rural setting of Madbury, NH, several miles outside of the City of Portsmouth. The 20 acre site is mostly covered with undisturbed vegetated land. Although clearing enough space for new construction would have been possible, there were several design constraints that greatly reduced the space available for construction. The new building was seeking LEED Certification, and was to be constructed within the requirements of the city’s recently adopted sustainability initiative. Both goals required that open, permeable space on the completed construction site be maximized, and disturbance of vegetated land be kept to a minimum. Additionally, the residuals management at the existing plant was inefficient and required large areas of the site to be available to accept the large sludge volumes produced by the aging plant. The existing plant provided a large portion of the city’s water demand, so taking the plant offline for any significant portion of time was not an option. The constraints required careful construction phasing coordination to construct several new process facilities in the same location as the existing process facilities they were replacing.

Construction commenced in May 2009 and the plant was placed online during the summer of 2011. During the startup phase, large volumes of water were required for disinfection, filter media installation and system testing. There was no available sewer connection at the remote site, so the contractor was limited to on-site disposal of the water. To overcome this obstacle, the contractor worked closely with the city personnel to operate the two plants in a variety of configurations, using the existing plant for retreatment of the testing water rather than disposing of it, resulting in both cost and schedule savings.

Since being placed online, the new plant has experienced increased filter run times and organics removal. Filter runs in the old plant would struggle to reach 40 hours during the summer months when organic matter in the raw water was at its highest. Run times at the new plant have been extended to 48-72 hours in the same raw water conditions, frequently at higher flow rates than produced at the old plant. Filter turbidities would tend to approach 0.3 ntu during the tail end of the filter runs at the old plant, but new filters remain steady throughout their filter run times, consistently operating well below 0.05 ntu. The new plant also displays improved organics removal, which will serve to help the city in meeting their regulatory disinfection byproduct compliance.

To request a copy of the full paper, please contact the author at mgreeley@hazenandsawyer.com.

Hear about new publications with our email newsletter

We will never share your details with anyone else.

Horizons

Newsletter Newsletter

Horizons Fall 2017 (pdf)

Horizons showcases significant water, wastewater, reuse, and stormwater projects and innovations that help our clients to achieve their goals, and can help you achieve yours. Articles are written by top engineers and process group leaders, demonstrating and explaining the beneficial application of a variety of technologies and tools.

View previous issues »